Service Delivery Timelines
Standard Applications (Below 25KVA)
1. Time taken to quote – 14 days
2. Time taken to approve wayleaves after payment – 14 days
3. Construction – 12 days
4. Metering – 2 Days
Total number of days – 43 Days
Premium Applications (Above 25KVA), excluding Small and Medium Entreprises (SMEs)
1. Time taken to quote – 7 days
2. Time taken to approve wayleaves after payment – 7 days
3. Construction – 13 days
4. Metering – 2 Days
Total number of days – 30 Days
Standard Applications (Below 25KVA)
1. Time taken to quote – 14 days
2. Time taken to approve wayleaves after payment – 14 days
3. Construction – 12 days
4. Metering – 2 Days
Total number of days – 43 Days
Premium Applications (Above 25KVA), excluding Small and Medium Entreprises (SMEs)
1. Time taken to quote – 7 days
2. Time taken to approve wayleaves after payment – 7 days
3. Construction – 13 days
4. Metering – 2 Days
Total number of days – 30 Days