PRESS RELEASE
10th October 2007
KPLC builds six new diesel power stations
Two diesel power generators destined for Mandera town power station in North Eastern Province arrived at the Jomo Kenyatta International Airport on Tuesday. The generators with a total capacity of 800 kilowatts will be installed in a Shs.40 million project being implemented by the Kenya Power and Lighting Company (KPLC) with funding from the government, to augment power supply in the important border town.
KPLC Chief Engineer for off-grid power stations, Mr Henry Gichungi, said installation of the two generators would be done immediately and the machines commissioned by end of October, bringing the total generation capacity at the station to 1,200 kilowatts. Currently, demand for power in Mandera town has outstripped supply that is provided by two ageing diesel generators.
KPLC is currently developing six new power stations at a cost of Shs.766 million in parts of the country that are not served by the national grid.
The stations, referred to as Off-Grid Power Stations, are being implemented with funding from the Ministry of Energy under the rural electrification programme. The stations are being installed at Mpeketoni in Lamu district, Hola town in Tana River , Elwak in Mandera South, Habaswein in Wajir South, Merti in Isiolo and Mfangano Island in Suba district.
Of the six stations, Mfangano will have the biggest capacity, generating 1.5 megawatts followed by Hola, Elwak, Habaswen and Merti which will generate one megawatt each. Mpeketoni station will have a capacity of 600 kilowatts.
At Mpeketoni, one generator is already up and running and is providing electricity to a section of residents. It was delivered by air and installed in September at the existing power house previously used by residents, to generate their own power. A second generator will be delivered this month to enhance generation to meet demand at Mpeketoni town, and at the nearby Witu trading centre.
Besides installing the new generators, KPLC is also undertaking installation of new control equipment, extension of power houses, installation of bulk fuel tanks and construction of electricity distribution lines.
Meanwhile, KPLC has completed upgrading works at Moyale and Lodwar off-grid power stations at the total cost of Shs.41 million, which has improved reliability of the power stations. The completion of upgraded projects will increase generation capacity of the stations, and hence create adequate reserve capacity to accommodate growing electricity demand in the short and medium term.
At the same time, KPLC is constructing medium and low voltage distribution lines in Pate Island adjacent to Lamu Island, to enable the community to benefit from power generated with generators bought with Constituency Development Funds. Construction of the lines is expected to be completed by October.
Ends
For more information, contact:
KPLC Corporate Communications Dept.
Tel: 3201622/28/29 or
Email comms@kplc.co.ke