Press Releases

Mombasa North power infrastructure upgraded

4th June, 2014

Electricity supply infrastructure in Nyali, Kisauni, Kongowea, Bamburi, Mtopanga and surrounding areas in Mombasa North got a shot in the arm today when hundreds of Kenya Power workers descended on the network to upgrade power lines, transformers and substations to reduce the occurrence of blackouts and also improve quality of supply.

 

Read More

Power restored following major outage

Electricity to all parts of the country has been restored following a system breakdown emanating from the Coast Region that caused a major power outage affecting many parts of Nairobi, Mount Kenya and Coast Regions.

Read More

Coast generation system causes major outage

26th May, 2014
A generation system breakdown emanating from the Coast Region has caused a major power blackout affecting many parts of Nairobi, Mount Kenya and Coast Regions. 

Read More

New generation project to lower power costs

7.05.2014

Energy and Petroleum Cabinet Secretary, Mr Davies Chirchir has reasserted the government’s commitment to make Kenya an attractive and competitive investment destination in Africa. 

Read More

Nairobi's Industrial Area power supply gets boost

11.05. 2014

 

Kenya Power today carried out a major operation within Industrial Area in Nairobi to improve the quality and reliability of power supply to customers in the area.

Read More

Kenya Power to spend Shs.1 bn to upgrade Nairobi industrial power supply

7.05.2014

Kenya Power has adopted a radical approach to enhancement of quality and reliability of power supply to the economy by opting to implement out-of-the-box solutions. 

Read More

Operation boresha stima viwandani launched

02.04.2014
Kenya Power has embarked on an operation through which it intends to improve the quality of power supply to its large power and domestic customers within the Industrial Area, Nairobi. The operation dubbed Boresha Stima Viwandani will be carried out over a period of 2 months and will involve master repair works such as the rehabilitation of jumpers and the realignment of high tension lines.

Read More

Thika Town’s power supply gets boost

13.04.2014
The quality of power supply to the industries and residents of Thika town is set to greatly improve following the completion of a 66/11 kv substation with two 45 MVA transformers at Makongeni. The ultra-modern facility, constructed by Kenya Power at a total cost of Shs.642 million, has adequate capacity to accommodate additional power demand by existing industries who would like to expand their operations, as well as new industrial and commercial enterprises.

Read More

Kenya Power to invest USD 600 million in power network

16.01.2014
The electricity distribution network will be strengthened to support heavy industrial and commercial use, with the injection of over USD 600 million in the next three years, Kenya Power Managing Director and CEO, Dr Ben Chumo said today.

Read More

The Kenya Power Manufacturers’, Technology and Innovation EXPO

6th-8th July, 2022 - KICC, Nairobi, Kenya


We are excited to be holding our inaugural Manufacturers’, Technology and Innovation Expo, scheduled for 6th to 8th of July, 2022 at the Kenyatta International Convention Center (KICC), in Nairobi, Kenya. The theme of the EXPO is Affordable, Clean and Sustainable Energy for all.

It will be open to local and international Original Equipment Manufacturers (OEMs), as well as technology providers in the energy sector, to showcase equipment and solutions that demonstrate business efficiency, cost effectiveness, quality service, and positive customer experience.

This high-level event comes at a time when Kenya, and indeed the region, is actively working to deepen electricity access while undertaking strategic investments to: improve power quality and reliability, deploying technologies to improve technical and operational efficiencies, and revolutionising customer service interactions.

This is happening as the energy sector undergoes major developments, such as the shift towards renewable energy, the increased adoption of e-mobility, and the drive to embed clean cooking practices as the global push to protect the environment gains momentum.

Exhibitors are therefore called upon to showcase bespoke, tried and tested solutions that will enable Kenya’s energy sector to enhance its internal efficiencies and deliver affordable power while providing a superior customer experience.

In addition, the event will offer participants an unrivalled platform to exchange ideas, benchmark against their peers, and identify potential areas of collaboration with like-minded organisations. We have therefore invited all the energy sector agencies in Kenya, generators, leading power utilities in the region, development partners, financiers, and regional and international trade partners, to participate.

We will therefore be greatly honoured to invite exhibitors to showcase their solutions during the EXPO. (Exhibition booths are available on first come, first serve basis). As a leading provider of innovative energy sector solutions, we are looking forward to a highly impactful engagement.

To get more information on how your Company can participate, please fill in your details in the online form, or kenyapowerexpo2022@kplc.co.ke, or call Salome Nduta +254711031642 or book a booth by making payments through the bank details provided below.

No. BOOTH SIZE COST (LOCAL EXHIBITOR) COST (INTERNATIONAL EXHIBITOR)
1.   9m2 (3m x 3m)  K.Shs. 100,000 $1,000
2.  18m2 (6m x 3m)  K.Shs. 150,000 $1,500

Expo Documents

  • Remarks by Amb. Dr. Monica K. Juma, (OXON) EGH, Cabinet Secretary, Ministry of Energy and Ag. Cabinet Secretary, Petroleum and Mining
  • Speech by Vivienne Yeda, Ogw, Chairman of the Board of Directors of Kenya Power and Lighting Plc.,
  • Speech by Eng. Geoffrey Muli, Managing Director and CEO (Ag.), Kenya Power and Lighting Plc During the Manufacturers’, Technology and Innovation Expo
  • Kenya Power Expo-2022 Presentations - Day 1
  • Kenya Power Expo-2022 Presentations - Day 2
  • Kenya Power Expo-2022 Ahsanteni! (Appreciation)

  • Click to download Floor Plan - PDF

    Click to download Kenya Power Banking Details - PDF


    Eng. Geoffrey W. Muli,
    Managing Director (Ag.)

    Kisumu high voltage power line collapses in heavy rain

    03.01.2013

    A heavy rain and wind storm that occurred at Ahero yesterday evening, pulled down four steel power pylons interrupting power supply to Kisumu City and environs.